Self-build home: Appoint a range of contractors and suppliers to construct the home
Introduction.
Where a self builder intends to co-ordinate the purchase of goods, materials and labour themselves, they may benefit from the services of a project manager or construction manager. This method of procurement carries with it the greatest risk in terms of keeping to budget and programme because responsibility is fragmented among many parties. The biggest challenge is sequencing the work in a way that minimises return visits and potential disruption. Problems of synchronisation can result in delays and claims for non-productive time.
Production information should be divided into trade 'packages' to obtain prices from individual contractors and suppliers.
When deciding how to divide the works into separate trade packages, the interfaces between packages must be carefully considered and constantly monitored. Elements can fall between packages (for example the flashing to a rainwater outlet). Responsibility and consequent liability for each element of the works must be clearly defined.
It is normal to get quotes from more than one supplier or contractor for each package of work.
Contractors and suppliers might be identified by:
- Advertising.
- Research.
- Recommendation.
- Existing relationships.
- During the design process.
Discussing the works with suppliers and contractors during the design process, before appointing them, can help identify those that are most helpful and can also highlight potential problems. Contractors and suppliers might also be able to suggest alternative approaches based on their experience.
Discounts may be available from suppliers, particularly for large orders (this may make it worth buying a range of items from a single supplier), or by registering with organisations such as the self-build portal to benefit from group discounts. See Self-build homes negotiating discounts for more information.
When appointing contractors and purchasing goods and materials, it is important to be properly organised, with files for:
- Requests for quotations.
- Submitted proposals and prices.
- Orders.
- Confirmation of orders, prices and delivery.
- Delivery receipts.
- Invoices (separating the VAT element on the direct purchase of materials).
- Accompanying product literature such as; assembly instructions, operating manuals, spares and consumables information, maintenance and repair depots.
- A ledger recording all payments and financial commitments.
- Receipts of payment.
Other issues to address when obtaining quotations and placing orders include:
- Allowing for cutting and wastage.
- Purchasing spares and consumables to take full advantage of purchasing power.
- Obtaining warranties wherever possible.
- Obtaining servicing and maintenance quotes at the same time to take advantage of competitive leverage. This might include; boiler plant, heat exchangers, security systems, sewage treatment systems, automatic gate systems, garden maintenance and so on.
NB Self-build homes and the conversion of non-residential buildings into dwellings may qualify to reclaim VAT paid on eligible building materials and services. See VAT refunds on self-build homes for more information.
NB Self-build clients are ‘domestic clients’ for the purposes of the Construction (Design and Management) Regulations (health and safety regulations generally referred to as the 'CDM Regulations'), and so the client's duties under the regulations will generally fall to the contractor on a project where there is only one contractor or to the principal contractor on a project where there is more than one contractor. However self-build clients can attract health and safety duties under Part 4 of the Regulations if they control the way in which construction work is carried out. See CDM for self-builders and domestic clients for more information.
Featured articles and news
Editor's broadbrush view on forms of electrical heating in context.
The pace of heating change; BSRIA market intelligence
Electric Dreams, Boiler Realities.
New President of ECA announced
Ruth Devine MBE becomes the 112th President of the Electrical Contractors Association.
New CIAT Professional Standards Competency Framework
Supercedes the 2019 Professional Standards Framework from 1 May 2025.
Difficult Sites: Architecture Against the Odds
Free exhibition at the RIBA Architecture Gallery until 31 May.
PPN 021: Payment Spot Checks in Public Sub-Contracts
Published following consultation and influence from ECA.
Designing Buildings reaches 20,000 articles
We take a look back at some of the stranger contributions.
Lessons learned from other industries.
The Buildings of the Malting Industry. Book review.
Conserving places with climate resilience in mind.
Combating burnout.
The 5 elements of seiri, seiton, seiso, seiketsu and shitsuke.
Shading for housing, a design guide
A look back at embedding a new culture of shading.
The Architectural Technology Awards
The AT Awards 2025 are open for entries!
ECA Blueprint for Electrification
The 'mosaic of interconnected challenges' and how to deliver the UK’s Transition to Clean Power.
Grenfell Tower Principal Contractor Award notice
Tower repair and maintenance contractor announced as demolition contractor.